WORK HISTORY  

 

  2011 Nov All rounder, rigger/operator
CMA Contracting

ERA RANGER MINE – NT

Working on the final demolition of the Old Sulphuric Acid Plant.

     
 

2011

Recuperation – spent time in Meekatharra & Cue, WA Gold fields
     
 

2008 Nov

Retired for Knee Surgery & Recovery (2½ years)
   
 

2008 Jun

Supervisor / Rigger
CMA Corporation

ARGYLE DIAMOND MINE – WA

Breaking down heavy mine equipment.
Loading Road Trains for transporting scrap metal back to Darwin.

   
 TOPback to top of page
  2008 Working Manager
CMA Corporation

ALCAN – RIO TINTO – Gove, NT

Final Stage of G3 Clean up. Picking up and processing all Scrap on site enabling a shipment of 4000 ton consisting of scrap & pipe. Over a period of about 2 years 15,000plus ton of Scrap was removed from this site.

     
  2007 Supervisor
CMA Metals

Alcan G3 Project, Gove, NT

Supervise all scrap metal movement on the Alcan site, handling all redundant caustic piping in safe manner for processing and down sizing. Plus the very successful carting, loading and shipping (September) of approx. 9000 ton of Scrap Steel from Gove.

   
 
  2006 Supervisor
CMA Metals

Alcan Gove, NT

In charge of the ship loading of 2000 Ton scrap steel.

   
 TOPback to top of page
  2006 Supervisor
Moltoni Adams / CMA / John Holland

BHP, Port Hedland, WA - Dolphins Project

In charge of barge unloading and cartage to lay down area - from the demolition of the BHP Wharf 'Dolphins'.

     
  2006 Working Supervisor
CMA Corporation

Alcan G3 Project, Gove, NT

Total Demolition of 3x 300 Ton Thickener Tanks.

     
  2006 Working Supervisor
CMA Corporation

Alcan G3 Project, Gove, NT

Total Demolition of 3x 300 Tong Thickener Tanks.

   
 TOPback to top of page
  2006 Rigger Crane Operator
CMA Corporation – Thiess

Alcan G3 Project, Gove, NT

Driving a Franna AT20 moving construction equipment around the construction site. This was a fill in job while waiting to start a demolition contract on site.
     
  2005 - 2006 Working Supervisor
Moltoni Adams Group – CMA Corp.

QAL Gladstone, Parsons Point, QLD

Calcination Plant – The total demolition of the Firing Floor Building including 4 x 400T Rotary Coolers and machinery. Demolition of the Firing Floor was completed successfully with no Injuries or damage to other working plant.
     
  2005 Project Manager
Moltoni Adams Group – CMA Corp.

CSBP Kwinana, Western Australia.

Supervision, Training, Planning and Execution to dismantle the redundant ammonia plant – Stages 1 & 2 were successfully dismantled over a period of 6 months. Approx 3000 ton of Plant and 3000 tonne of Concrete was removed from site.
   
 TOPback to top of page
  2005 Working Supervisor
T&T Metal Trading Pty Ltd - NSW, Australia

Incitec Pivot Manufacturing plant Geelong, VIC, Australia.

The total demolition of a sulphuric acid plant. Heat exchange towers, scrubbers, pipe bridges, fibre insulation and asbestos removal some of which was along side working plant.
     
  2004

Chief Rigger / Seaman
Seaworks NZ / Saudi Aramco

Installation of power & fibre-optic cables at Abu Safah oil field, Saudi Arabia, Persian Gulf working from MV Vicky II.

   
  2004

Rigger / crane driver
Australian Defence Industry (ADI) / Waycon Services - Sydney, Australia

Duties included:
· Crane Driving TADANO TR 250 EX
· Refit HMAS SYDNEY

   
 TOPback to top of page
  2004 - 2003

Sub-Contractor
Jurgens Contracting/Macaulay Metals: Contracted to Methanex New Zealand, Motanui.

My responsibilities include;
· Supervision
· Training
· Planning & Execution to dismantle the 'Methanol to Gasoline' plant.

Stage One - completed August 2003
This was a 6 month project in which 4,500ton of plant was dismantled and processed to pot size for scrap.

Stage Two - commenced September 2003
This stage took 6 months in which 5,000+ton of plant was succesfully dismantled for scrap.

   
 TOPback to top of page
  2003

Sub-Contractor
Seaworks NZ Ltd - Wellington, New Zealand

Ras Laffan, Qatar, Persian Gulf
Worked on the cable laying ship MV Searanger laying 1,200-tons of power cable from NPF North field rig - 40 kilometres west for power to a jack-up rig.

   
  2002

Rigger / Crane Driver
Australian Defence Industry (ADI) / Waycon Services - Sydney, Australia

Situated at the Garden Island Dockyard, NSW, Australia rigging on the ships; HMAS Sydney & Success

     TOPback to top of page
  2002

Sub-Contractor
Seaworks NZ Ltd - Wellington, New Zealand: Contracted to Transpower NZ on the cable laying ship MV Searanger.

Building and setting up cable tank & cable handling equipment plus laying x2 sub-sea fibre optic cables across the Cook Strait, from Otrahonga Bay to Fighting Bay.

     
  2002 Rigger / Crane Driver
Australian Defence Industry (ADI) / Waycon Services - Sydney, Australia

Situated at the Garden Island Dockyard in NSW, Australia my duties included:-
  · Crane Driving TADANO TR 250 EX
  · Rigging on ships HMAS Newcastle & Manoora, plus Sydney Harbour Ferry's.
     
  2002 Rigger Fitter
Jord Engineers

British American Tobacco in Pagewood, NSW, Australia.
Removal of old heat exchanger and installation of a new heat exchanger in the Diet Plant process.
     TOPback to top of page
  2002 Rigger
Waycon Services - Sydney, Australia

BHP Port Kembla, NSW, Australia.
Shutdown, removal and replacement of wheels and shafts on the Sinter cooling plant.
     
  2002 Rigger Fitter
Australian Defence Industry (ADI)

Located in the Garden Island Dockyard, NSW, Australia the 2001 docking of the tug 'Korimul'.
  · The removal and replacement of Sea Cocks, Valves and Propellers on the floating dock.
     
  2001 Sub-Contractor
Seaworks NZ Ltd - Wellington, New Zealand
Working as a Rigger, Diver and Plow personnel in the Caribbean Sea, South America.

Laying fibre-optic cable on the 'ARCOS-1 Marine Installation'
a) Link 11-2 from Riohacha to Rio Magdalena, Columbia
b) Link 6 from Punta Cana to Puerto Plata, Dom. Republic, West Indies.
c) Offshore cable recovery & repair, Nicaragua.
     TOPback to top of page
  2001 Rigger Fitter
Waycon Services - Sydney, Australia

· Steelwork construction of flue and hood of No: 8 furnace.
· Lifting the hood and flue into position then connecting flue piping to the main stacks at the KAAL   Australia, Yennora Plant, NSW, Australia.
     
  2001

Rigger Fitter
Waycon Services - Sydney, Australia

Located in the Garden Island Dockyard, NSW, Australia the 2001 docking of the vessel 'Spirit of Tasmania'.
  · The removal on No: 1 & 3 main clutches, plus No: 4 main coupling from the main engine room,     off the ship to the workshop for overhauling, then back onto the ship and into position.

     
  2001 - 2000 Sub-Contractor
Seaworks NZ Ltd - Wellington, New Zealand: contracted to Telstra Saturn, then contracted to Telecom NZ Ltd

· Working as a Diver, Rigger, Launch & Recovery personnel and Cable Handler for the submersible   Sea Stallion2
· Plough on board the cable laying MV Searanger.
· Our job was to lay the fibre optic cable around the New Zealand coast.
     TOPback to top of page
  2000 Rigger / Fitter Welder
Abigroup - Sydney, Australia

· Shutdown and maintenance at Smithfield Visy Paper & Recycling Plant.
     
  2000 - 1999 Rigger Fitter
Waycon Services - Sydney, Australia

· Erecting and fitting of new baggage handling conveyor systems at the Sydney International   Terminal, MascotAirport.
     
  1999 - 1998 Manager
T&T Metal Trading Pty Ltd - Port Kembla, NSW, Australia

· Further demolition carried out on Christmas Island (located in the Indian Ocean) of a further 11   bulk fuel storage tanks and the taking out of more disused mind conveyors, buildings.
· Burning 3,000 cars, trucks & machinery, processing all to mill size.
· The removal of scrap for the Island required the processing of all stock piled scrap and the   successful carting, loading and barging from the Island of approximately 6,000-ton of scrap.
     TOPback to top of page
  1998 Working Site Manager
T&T Metal Trading Pty Ltd - Port Kembla, NSW, Australia

This job involved liasing with Government and Mine officials during the dismantling and demolition of an old rail system, bridges, hoppers, buildings, conveyors, bulk stores, fuel lines, as well as fuel oil tanks and associated equipment on Christmas Island located in the Indian Ocean.
· All scrap was taken to a central laydown area for further processing.
· Approximately 6,000-ton of scrap
     
  1997 Sub-Contractor
McConnell Smith Ltd

Marsden A & B Power Station Dismantling situated in Northland, New Zealand I worked as a Leading Hand, Rigger and Gas Cutter on the dismantling of 3,500-tons of structural steel and power station machinery, including oil pipe lines and pump stations.
· This job was concluded with the successful felling by use of explosives on x2 122metre (400ft)   concrete chimneys.
     
  1997 - 1996 Diver / Rigger
Seaworks Ltd - Wellington, New Zealand

Surveyed & repairs on sub-sea power cables situated in the Cook Strait, New Zealand.
     TOPback to top of page
  1995 Sub-Contractor
Jurgens Demolition - Wanganui, New Zealand

I worked as a Rigger/Gas Cutter dismantling the top 40ft of a 120ft building for Pastoral Foods in Eltham. The building was of steel construction with hoppers on the top floor.
· This job was successfully completed well within the time allocated.
     
  1994 Sub-Contractor
Jurgens Demolition - Wanganui, New Zealand

· Demolition of 'Moerewa Freezing Works' situated in Northland, New Zealand.
· Worked as a Crane operator on a NCK and a D750 Komatsu Dozer plus gas cutting.
     
  1993

Sub-Contractor
Mackenzie Salvage (NZ) & NPC - Nauru Island

Stage One: Reef blasting a trench in preparation for a pipeline from the edge of the reef in Nauru Island located in the Central Pacific to the shore for a decelination plant. I was in charge of the blasting and operated a PC400 Komatsu Digger with a Rock Breaker.

Stage Two: To lay and concrete a 600mm pipe in place.

· This job was conducted, successfully, amid 'trying' conditions.

     TOPback to top of page
  1993 Sub-Contractor & Site Manager
Mackenzie Salvage (NZ) & AGL Australia

Dismantled x2 Gasholders at the AGL Gasworks site situated in Mortlake, Sydney, Australia. One of these Gasholders was the largest ever built being 91.4 metres in diameter and 61.6 metres high, the second holder was 73.2 metres in diameter and 45.7 metres high.

· The job was completed 4 months ahead of schedule.
     
  1992 Partnership
Ray Hatch Contracting & NZ Diving & Salvage contracted to BP New Zealand Ltd.

Demolished 6 steel fuel-holding tanks in Gracefield, New Zealand. The steel was for re-use.
     
  1992 Built my own 2,800 sq.ft home between January and April
     
  1991 Diver & Rigger
Telecom New Zealand

Trans-tasman Fibre Optic cable. Bringing ashore the New Zealand end of the cable at Muriwai Beach, Auckland, New Zealand.
     TOPback to top of page
  1991 Sub-Contractor
Diver, Rigger & Supervisor
GK Shaw Building & Construction

Wharf and underwater repairs to piles. Re-sleeve rotten piles using grout bags on Shed 3, Queens Wharf, Wellington, New Zealand.
     
  1991 Diver, Rigger, Jetting Supervisor
Divers World Salvage, Wendell Perry, ABB Cables & Transpower New Zealand.

Laid and buried (to a depth of .6m) 5 sub-sea power cables in the surf zone from the beach to 200m seaward in the Cook Strait, New Zealand
     
  1990 - 1987 Oyster Farmer
Keri Keri, Bay of Islands, New Zealand.
     
  1986 Diver & Rigger
Divers World Salvage, Salvage Pacific & Engwirda Salvage Queensland

Recovery of oil and valuables located on the 'Mikhail Lermontov' in Port Gore, New Zealand from the 'Little Mermaid' salvage vessel.
     TOPback to top of page
  1986 Salvage Diver
Divers World Salvage & Baltic Shipping Company

Survey work for the Auckland firm McKay Shipping on the 22,000-ton sunken passenger liner 'Mikhail Lermontov' in Port Gore, New Zealand.
     
  1985 Diver
Divers World Salvage & NZ Electricity Department

Damage & stability survey of sub-sea power cable in the Cook Strait, Wellington, New Zealand.
     
  1983 Diver & Rigger
Divers World Salvage & Balfour Kilpatrick

Repairs and maintenance on the sub-sea power cable in the Cook Strait for NZ Electricity Department, Wellington, New Zealand.
     TOPback to top of page
  1983 Contractor
Wellington Harbour Board - New Zealand

Salvage and disposal of the 300-ton 'Yung Pen' Japanese Squid Boat in Wellington, New Zealand
     
  1982 Builder
Formed a partnership with 'John Knotts & Associates Builders' in 1982 and we were contract Builders within the Wellington area.
     
  1982 Sub-Contractor & Site Foreman
Fitzroy Transport - New Plymouth, New Zealand

Demolished 'The Midland Hotel' situated in Lambton Quay, Wellington.
     
   1981 Contractor
Wellington Harbour Board

Cut up and dispose of the 600-ton dredge 'Kerimoana' whilst still afloat.
     TOPback to top of page
   1981 Diver
Divers World Wellington Ltd - Wellington, New Zealand

Salvage and disposal of 'MV Millarm'.
     
   1981 Sub-Contractor
Divers World Wellington (New Zealand) & Selco Salvage Ltd (Singapore)

Salvage work to re-float the stranded 11,000-ton Bulk Carrier 'Pacific Charger' in Wellington, New Zealand
     
  1981-1980 Contractor: Blasting specialist Team Member
New Zealand Government

This was a 6-month project that involved blasting channels in the reefs to allow workboats to the Island of 'Tuvalu', located within the 'Alice Island' group in the Central Pacific.
     
  1980 - 1979 Contractor
Wellington Harbour Board - Wellington, New Zealand

Disposed of 30 Harbour Cranes each weighing 90-ton for scrap.
     TOPback to top of page
  1979  Manager
John Gapes Demolition & Fletcher Construction - Wellington, New Zealand

Demolished and disposed of 'ANZ Bank' site which covered a city block of 7 buildings along Featherston Street & Lambton Quay. These buildings ranged between 8 - 10 storeys high.
     
  1979  Manager
John Gapes Demolition - Wellington, New Zealand

Demolished and disposed of the 9 storey 'The Grand Hotel' on Willis Street.
     
  1979  Manager
John Gapes Demolition - Wellington, New Zealand

Demolished and disposed of the 10 storey 'CML Insurance Company' building to make way for a new building.
     
  1979 Manager
John Gapes Demolition - Wellington, New Zealand

Demolished and disposed of the 'Borthwicks Freezing Works' in Waitara after a fire.
· 20 men on site.
     TOPback to top of page
  1978  Sub-Contractor
Fitzroy Transport - New Plymouth

Demolished and disposed of 'Ngauranga Meat Company' - 10 acres of buildings using explosives and machinery
     
  1978-1977 Manager
John Gapes Demolition - Wellington, New Zealand

Demolished & disposed of 13 storey 'Inland Revenue' building situated in the Wellington central city.
     
  1977  Diver
Divers World Wellington Ltd - Wellington, New Zealand

Salvaged the vessel 'Waimana' - a 60ft trawler in Wellington.
     
  1977 Manager
John Gapes Demolition - Wellington, New Zealand

Demolished & disposed of 6 storey 'Hannah's Building' after a fire in Willis Street, New Zealand
     TOPback to top of page
  1976  Contractor
Shelly Bay Slipways & Divers World Wellington Ltd - Wellington, New Zealand

· Re-construction of wharf & slipway
· Replaced underwater bearers and slip rails
     
  1976 Sub-Contractor
Machinery Salvage - Auckland, New Zealand

Salvaged, re-floated & repaired the 'Choryo Maru' (no 652) a 300ton Japanese squid boat in Wellington, New Zealand
     
   1975 Manager
John Gapes Demolition - Wellington, New Zealand

Demolished and disposed of 'The Duke Hotel' - 5 storeys, Willis Street, Wellington.
     TOPback to top of page
  1975 Manager
John Gapes Demolition - Wellington, New Zealand

The following were the larger demolition and disposal jobs:
· The Duke Hotel - 5 storeys
· Hannahs Building - 6 storeys
· Inland Revenue Building - 13 storeys
· Borthwicks Freezing Works
· CML Insurance Building - 10 storeys
· The 'Grand Hotel' - 9 storeys
· ANZ bank - whole city block
     
  1973 Sub-Contractor - Wanganui, New Zealand
L Doyle Scrap Metals

Demolition of Railway 'Viaduct Bridge' situated at Ratahi, Ruapehu National Park area
     
  1972 Sub-Contractor - Wellington, New Zealand
Proctors Reclaim

Salvage & disposal of the trawler 'Hautapu' (300 ton)
     TOPback to top of page
  1971  Sub-Contractor - Wellington, New Zealand
Pacific Scrap / Proctors Reclaim

Salvage & disposal of 'MV Wahine" (10,000 ton)
     
  1971 Contractor -
Wellington Gas Works

· Disposed of x2 2,000ton Gas tanks
· Disposed of x2 Retort (5 storey) houses
· Disposed of x1 Engine room & buildings
Approximately 15 acres of buildings, tanks & 5,000 ton of scrap & machinery was removed from the site
     TOPback to top of page
  1970 Leading Hand, then Foreman (staff of 15) - Wellington, New Zealand
Samuals Demolition

Disposal of 20 oil holding tanks & refinery at Mobil Oil Gracefield Plant
     
  1969  Bushman - Murupara, Kaingaroa State Forest, New Zealand
Kaingaroa Logging Company
     
  1969 Builder - Wellington, New Zealand
CR Hatch Builder
     
  1966 Builders Apprentice - Wellington, New Zealand
Upton & Shearer Building Contractor
     TOPback to top of page